SK and AWS Break Ground on Ulsan AI Data Centre With a Late-2027 Opening Target

Chey Tae-won's talks with Andy Jassy became a signed cloud-infrastructure project and an August groundbreaking. By July 2026, construction continued as SKT widened its national infrastructure strategy.
SK and AWS signed their Ulsan data-centre agreement on 20 June 2025, establishing a 15-year partnership. SK would lead construction and AWS would establish an AI Zone. The project brought a global cloud platform to a location where SK already had land, fuel infrastructure, electricity generation and network connections.
Ulsan's significance lies in that combination. SK's industrial presence gave the project a physical starting point outside the Seoul metropolitan area, while AWS supplied a defined cloud service and demand relationship. The signing followed negotiations led by Chey Tae-won and moved into a groundbreaking ceremony two months later. It became an early project in SKT's widening effort to make infrastructure a business alongside its AI services.
The commercial decision joined assets that previously served different parts of the group. SK Broadband acquired former SK Chemicals land; SK Multi Utility supplied the identified electricity route; SK ecoplant and SK AX contributed construction and building systems. AWS brought the AI Zone. That allocation of work, followed by construction, is the concrete business development behind the partnership's fifteen-year term.
Chey Took SK's Industrial Offer to Andy Jassy
SK's August account traces the project to Chey's first meeting with Amazon chief executive Andy Jassy in June 2024. Chey presented a group able to supply semiconductors, energy, data-centre construction, operations and service development. He argued that those capabilities made SK a suitable partner for an AI-dedicated facility in north-east Asia. The talks began with that group-wide proposition, not an isolated property development.
Chey met Jassy twice more, according to SKT, while the working teams held roughly thirty in-person and online discussions through May 2025. Those exchanges brought the affiliates' different capabilities into the same project: energy suppliers, the landowner, network operators and builders. The June contract followed that year-long sequence. Chey's proposal had become a partnership with defined responsibilities for SK and AWS.
An Industrial Site Came With a Fuel and Electricity Route
SKT executive Ha Min-Yong's July 2025 column set out the location decision in practical terms. SK Broadband had acquired land previously owned by SK Chemicals. In Ulsan's Bukshin Port area, SK Gas operated LNG terminals and LPG storage; SK Multi Utility operated a 300 MW LNG combined heat and power plant. Ha said a large-scale electricity supply had been secured for the data centre.
The network plan connected Ulsan with the Seoul metropolitan area through SKT and SK Broadband's domestic lines, and with overseas routes through SK Broadband's submarine cable in Busan. Ha put the international landing station around forty kilometres away. He also credited cooperation with Ulsan city and the Korea Industrial Complex Corporation for approvals. The location brought together an industrial site, a large electricity supplier and domestic and international connectivity outside the capital region.
The June Ceremony Joined That Site to AWS's Cloud Service
At the June signing, Chey and SKT chief executive Ryu Young-sang were joined by AWS infrastructure-services vice-president Prasad Kalyanaraman, Asia-Pacific and Japan executive Jaime Valles and Korea managing director Ham Kee-ho. The agreement assigned SK the construction lead and AWS the AI Zone. Its proposed offer included AWS infrastructure and servers, UltraCluster networking, SageMaker, Bedrock and Amazon Q.
SKT's July account places the public launch at the Ulsan Exhibition and Convention Center. SK Broadband chief executive Park Jin-hyo and Kalyanaraman took part in the signing there. The exhibition showed operating tools including AIDC SecureEdge, AIDC Infra Manager and Petasus Cloud, with Rebellions, Studio Lab and TwelveLabs also demonstrating technology. This was a public presentation of the ecosystem around the planned facility.
Ulsan also occupied a specific place in SKT's infrastructure programme. The company had opened its Gasan GPU-as-a-service operation in December 2024; hyperscale capacity, GPU services and edge AI were the three strands described in its July explanation. The new project extended that programme into a dedicated location built for dense AI equipment. Hybrid air and liquid cooling and data-centre infrastructure management formed part of the planned operating design.
- SK Telecom / SK Group and AWS Ulsan agreement
- SK Telecom / July infrastructure account, rack cooling density and Gasan launch
- SK Telecom / AI data-center executive's project discussion
Reported Metrics
- Stated partnership duration: 15 years. Partnership term stated in the June 2025 Ulsan AI Zone announcement. Source 1
- Expected commencement of operations: 2027. Operation-start target in the June 2025 project announcement. Source 1
Groundbreaking Followed With the Builders and City Present
On 29 August 2025, SKT and SK ecoplant held the groundbreaking with AWS and Ulsan city. Roughly two hundred attendees included SK SUPEX Council chairman Chey Chang-won, Ryu, SK ecoplant chief executive Kim Hyung-keun and Ulsan mayor Kim Doo-gyeom. The attendance reflected the next stage: a contracted project becoming a construction undertaking involving the group, its cloud partner and local government.
SK ecoplant described advance work on construction methods, major equipment, power, air conditioning, communications and cooling. Ha's earlier account had assigned SK AX mechanical, electrical and plumbing capabilities and drawn on SK Broadband's operating experience. SK ecoplant chief Kim Hyung-keun linked the work to its effort to build a position in the emerging AI data-centre market. The project gave the group's construction and energy businesses a shared assignment alongside its telecoms companies.
SKT also signed an MOU with Ulsan city at the groundbreaking. It covered attracting customers, regional economic activity and jobs, and the ambition to extend the first hyperscale facility into a gigawatt-scale cluster. For a city long associated with manufacturing, the proposed connection was between new computing infrastructure and existing industrial activity, including digital twins and factory automation. Those local ambitions accompanied the construction start.
- SKT / Ulsan groundbreaking ceremony and affiliate roles
- SK Telecom / AI data-center executive's project discussion
Jung's 2026 Strategy Kept Ulsan as the First Project
By 5 July 2026, SKT still described Ulsan as under construction, now targeting the second half of 2027. Its Korean update linked the project to the roadmap chief executive Jung Jai-hun had presented at SK AI Summit in November 2025, including a longer-term Ulsan expansion beyond one gigawatt. The first facility remained a project with its own construction timetable inside that larger programme.
The July strategy proposed a south-eastern cluster exceeding 2 GW and another 1 GW in the south-west, within a plan to open 5 GW in stages from 2029. Its longer ambition reached up to 15 GW, with the Korean account describing expansion towards 2035 according to demand and investment conditions. SKT would lead design, construction and operations across the group.
The English release named partner investment, long-term customer contracts and project financing alongside company investment as prospective funding routes. The Korean account placed the wider plan within balanced regional development and the government's ambition to become a leading AI nation. Ulsan supplied an existing construction project around which Jung could organise that strategy. SKT's role was expanding from selling telecoms services towards coordinating the group's factories, power, networks and construction expertise for computing customers.
- SKT / July 2026 Korean update: Ulsan construction, H2 2027 target and wider phased plan
- SKT / English July 2026 programme: wider capacity ambition and prospective financing routes
The first Ulsan facility was still under construction in July 2026, targeting the second half of 2027. Later gigawatt additions would follow demand and investment conditions. Ha's proposed electricity-cost advantage therefore remained an operating expectation, with the 300 MW figure describing the supplying power plant.
Primary Sources
- SK Telecom / SK Group and AWS Ulsan agreement (2025-06-22)